Cologne Worringen, Germany
Period: | Jan. 2014 to Apr. 2014 |
Client: | INEOS GmbH |
Project description: | Feasibility study for installation a new cogeneration power plant with steam supply to the steam manifold for the demand of the common chemical plant.The new cogeneration power plant comprises a gas turbine, a supplementary fired HRSG, a back pressure turbine and the BoP for the new installation. The priority of the new cogeneration power plant is to burn, respectively to dispose several gases from chemical processes, without an exceeding the required emission values in to the atmosphere, which are stipulated by law as well as feeding steam into the manifold of the common chemical plant. Generation of electrical power has no importance. Special challenge: Installation in an existing plant, which has to continue operation during the implementation activities. Feasibility study for installation a new cogeneration power plant with steam supply to the steam manifold for the demand of the common chemical plant.The new cogeneration power plant comprises a gas turbine, a supplementary fired HRSG, a back pressure turbine and the BoP for the new installation. The priority of the new cogeneration power plant is to burn, respectively to dispose several gases from chemical processes, without an exceeding the required emission values in to the atmosphere, which are stipulated by law as well as feeding steam into the manifold of the common chemical plant. Generation of electrical power has no importance. Special challenge: Installation in an existing plant, which has to continue operation during the implementation activities. |
Tasks: | Thermodynamic calculations, boiler design by using an own boiler calculation program, conceptual evaluations, preparation of a time schedule and cost estimation of the new installation. |